Normally a clarifier runs at one torque value for 90 to 98 percent of the time. This torque value could be termed the "running torque" of the clarifier. Sometimes the running torque is called the "design torque". The drive unit should be designed for this running torque, which will give the most economical mechanism based on the intended use of the clarifier.
The drive unit should be protected from excessive loads that would require it to run
above its design requirements. An alarm should be set that provides adequate
protection, and tells the operator that there is something affecting the
clarifier mechanism. This alarm setting should be above the running torque; 120%
of the running torque is generally sufficient.
Use of an
alarm torque value is beneficial not only in protecting the drive unit, but
also in giving an added range of running torque in case the loading values were
incorrectly selected. The drive unit
should not be designed to run continuously at or near the alarm setting. This
would defeat the reasoning behind choosing the running torque requirement.
For the
protection of the drive unit, a shut-off or cut-off torque rating should be
used. If there is some abnormality in the clarifier causing a rapid increase in
torque, the unit would shut itself off without adversely affecting the
mechanism. Shut-off torque should be
used only as a protective rating, however, and the unit should not be running
continuously at this value; 140% of the running torque appears to be adequate.
If the drive was sized and designed to run continuously at this value, it would
be over-sized and therefore an uneconomical choice consideration.
Peak torque
is the value determined by the supplier of the drive unit indicating what the
unit can handle at a momentary or instantaneous load. This ultimate load should
be of very short duration, e.g. in the three (3) second range, in case the
torque is increased so rapidly that response time to the shut-off mode is not
enough. Peak torque is normally two (2) times the running torque.
As described
above, an overload device is essential for the drive unit so that the alarm and
shut-off torques can be sensed and the unit protected. This is particularly
important in the larger units because a good deal of money is invested in the drive
and adequate protection is critical. Overload protections can be electronic and/or
mechanical. On the smaller drive units, such as those that rest on the bridges
of small clarifiers, the complete range of protection is not as critical. A
simple shear pin device that turns the unit off when an excessive torque is
sensed is generally adequate.
As engineers
and designers progress in their determination of the drive units to be furnished,
they should remember that reputable equipment suppliers stand behind their
drives. It is apparent by the operation of the clarifier if the drive is
working properly. However, if project
engineers state a torque value above the necessary range, they want to be assured
of the results. Therefore, the specification should clearly state desired
torque ratings: running, alarm, and shut-off.
As an
additional requirement for a project, a torque testing procedure could be
specified if required. This is a costly
procedure for most projects, but if the engineer feels he or she is not getting, or
will not get the drive that was specified, he or she could call for torque testing of the
drive unit in the field.
Monday, June 18, 2012
Friday, May 25, 2012
Clarifier Drive Torque: Selection and Clarity by William H. Boyle, P.E.
In order to
provide an accurate determination of torque for specific applications,
specifying engineers should be familiar with the application, selection, and terminology
related to drive torque requirements. Also, required design specifications
should be clearly communicated to suppliers.
Torque Calculation
Loading varies with the type of waste to be
handled, material density, depth of sludge, and angle of repose of the solids, as
well as other intangible parameters. Loadings for various industrial sludges
are sometimes available based on pilot work or field data. The following table
shows suggested uniform loadings (L) in lbs/ft. for various sewage treatment
applications.
There are times the skimmer could be hung up on the scum trough and possibly impart a torque to the center mechanism and subsequently to the drive unit. This is not a major factor since the skimmer and the supports would act as a torsion-bar (in most cases) and dissipate the torque energy, causing a mechanical failure before it got to the drive unit. There are some designs that use a fail-safe release to minimize this concern.
The dictionary
definition of torque is “a force or combination of forces that produces a
twisting or rotating monitor.”
When engineers
specify a particular torque value for a clarifier, they are limiting the
suppliers to one particular design requirement. By selecting and specifying a
torque, the designers are trying to assure the drive will function as intended.
To truly receive what they are specifying, specifications should be made clear
and simple.
In the
circular clarifier field, the types of drives vary with each equipment
supplier. The basic arrangements are: (1) the half bridge design where the
drive rests on the center column; (2) the full bridge design where the drive
rests on the bridge spanning the tank. While other arrangements do exist, the
two described above are most commonly seen in the circular clarifier
field.
Calculation
of torque for a circular drive unit is based on the simple cantilevered beam
type of equation, with a uniform load L (#/ft. – pounds per foot) applied to
the rotating sludge removal arm. Torque required to turn a rake arm would equal
the resultant force of the uniform load (L*R) [R, Radius of the basin]
multiplied by the moment arm (R/2). Since most circular clarifiers have two
arms, the resulting equation will be T = L*R^2 (expressed in ft•lbs [foot pounds]).
Application
|
Loading L - #/ft.
|
Grit
|
40
|
Primary w/grit treatment
|
8
|
Primary w/o grit treatment
|
10
|
Secondary (scraper)
|
6
|
Secondary (suction)
|
4
|
Gravity Thickener primary only
|
30
|
Gravity Thickener primary w/ secondary
|
20 - 30
|
Torque = L*R^2 = foot pounds Radius R in ft.
|
There are times the skimmer could be hung up on the scum trough and possibly impart a torque to the center mechanism and subsequently to the drive unit. This is not a major factor since the skimmer and the supports would act as a torsion-bar (in most cases) and dissipate the torque energy, causing a mechanical failure before it got to the drive unit. There are some designs that use a fail-safe release to minimize this concern.
Wednesday, May 9, 2012
Riser Pipe Sludge Box and Inlet Design Considerations by William H. Boyle, P.E.
The riser
pipe sludge removal design raises some concerns with regards to the inlet
distribution into the final clarifier. Based on the inherent need for a sludge collection
box, the inlet for the mixed liquor flow is introduced into the clarifier well below
the water surface. The influent well depth is then lowered accordingly, and the resulting
effect on the side water depth is a key element to be considered.
To help minimize the jetting effect of the riser
pipe baffle wall, simple energy dissipating baffles can be utilized. However, the
traditional energy dissipating inlet (EDI) well design of a tub with a floor
must take into account the maintenance and replacement of the sludge seal
between the sludge collection box and center influent column.
Taking these design considerations into account will ultimately produce a more efficient, well-balanced riser-pipe clarifier.
It is
imperative to have the sludge collection box be as shallow as possible. This will
minimize the headloss required yet still allow for proper uniform sludge pick
up and adequate flow velocities within the riser pipes.
In addition, the arrangement
of the riser pipes at the inlet of the sludge collection box creates a baffle
wall that produces a strong, defined flow jetting pattern. As a result, the
sludge pulsates as it enters the clarifier because the baffle walls block the
inlet ports. This resulting flow pattern accentuates the normal sludge flow
pattern (sometimes called the wall effect) in the final clarifier.
Robert
Crosby recognized the wall effect and did something about it. He and Jeanette Siemens (Brown) developed the
energy dissipating wall baffle at the Stamford Connecticut WWTP.
Taking these design considerations into account will ultimately produce a more efficient, well-balanced riser-pipe clarifier.
Monday, April 9, 2012
Riser Pipe Sludge Removal Design Considerations by William H. Boyle, PE
The riser pipe as developed in the early 1960s went through a number of design iterations for sludge removal. Due to the lack of concern for uniform floor pick up by the original designers, the original riser pipes were such that each pipe was of the same diameter and was adjustable to vary the return sludge flow. The design allowed the operator to adjust each pipe for the perceived conditions that might be found at various points within the clarifier. This flexibility to remove sludge from the various areas in the basin was thought to be paramount. Although this flexibility was and is a good design feature, other problems associated with the pick up of the sludge manifested themselves in the field.
One of the major drawbacks was that low velocities caused solids deposition and blockage within the pipes and elbows at low flow conditions. This became a major problem for some of the installations that utilized the riser pipe design. Also, there were problems due to the increased headloss that was required for some flow control devices (particularly the telescopic sludge valve type). Since it was most economical to go with a single size for the withdrawal pipes and space them equally on the radius of the basin, uniform pick up of the sludge was compromised.
Wednesday, March 21, 2012
Riser Pipe by William H. Boyle, PE
The riser pipe sludge removal device was developed in the early 1960s. At the time, Rex Chain Belt (now Envirex/Siemens) patented the current Tow-Bro™ / unitube header product. As a result, hydraulic removal for activated sludge final clarifiers became the standard. To overcome this patent and still hold to hydraulic removal of activated sludge, the riser pipe design was developed and promoted. It was marketed and furnished heavily in the Northeast part of the USA by Dorr-Oliver, Walker, and Eimco who were the main players at that time. There have been various names for the product over the years such as: riser pipe, pipe organ, site well clarifier (so that it can be seen when there is a clogging problem), and suction removal pipe device.
The general thinking was that a competitive offering was needed that could overcome the dominance of the Tow-Bro™ with unique features that it did not include. The riser pipe offered the plant operators the ability to see the sludge in the sludge box and the ability to control the sludge withdrawal rate from each area/region in the tank. There are several different flow control device designs for the pipes as they discharge into the sludge box. The two main control layouts are: 1) individual compartments with a submerged orifice gate and 2) a pipe over pipe design with a submerged orifice to control flow by varying the size of the orifice.
Despite these unique design features, there was not a lot of concern given to uniform pick up of sludge, the size of the pipes, low flow velocities, or pipe clogging problems. There were also thoughts at the time that the heavier sludge settles out near the center of the basin, making uniform pick up across the basin diameter less critical. There were some designers that also specified and promoted a heavy solids line at the center of the tank with scrapers directing the sludge into a heavy solids hopper. The outer area towards the wall then would be considered for the riser pipe removal of sludge.
After the Tow-Bro patent ran out in the mid-to-late seventies most manufacturers furnished the same header design configuration as the Tow-Bro™. The original equipment will now be 20 to 40 years old and in need of replacement at many plants.
Subscribe to:
Posts (Atom)